Application for Environmental Impact Assessment
Contractors in need of an EIA should follow the below set guidelines and procedure
EIA PROCEDURE
Registration:
1. Project proponent should submit evidence of payment to Federal Ministry of Environment, Environmental Assessment Departmentand collect project registration/Notification form.
2. Proponent return completed EIA registration form with EIA Terms of Reference (ToR) and comprehensive project proposal for the proposed project to the ministry.
Initial Environmental Examination (IEE)
1. Site verification of the proposed project location is conducted by the Ministry
2. Scoping of the project
3. EIA screening of the project scope and ToR alongside with the report of the site verification for the EIA categorization
Evaluation and Analysis
1. The EIA study is carried out including baseline environmental data gathering and laboratory analysis of collected samples witnessed by the Ministry –two seasons.
2. Submission of hard copies (depending on magnitude & category) and electronic copy of the draft EIA report to the Ministry.
3. The draft EIA report is display for public review and participation depending on EIA category the report is classified. (see 3b above)
4. The draft EIA report is reviewed by independent Panel of Experts with relevant regulators (the review level depends on the category of the project).
5. The approval or disapproval of the EIA of the product by the Ministry base on the recommendations of the independent panel of experts.
6. The final EIA report is produced by the proponent
7. Submission and approval of the final EIA report for issuance of EIA certificate and EIS. Impact Mitigation Monitoring (IMM)
8. Impact Mitigation Monitoring is carried out on the project by the Ministry in collaboration with states MENV and Local Government s to ensure the implementation of:
* Conditions of approval
* Implementation of mitigation measure
* EMP
9. At the commissioning of the project decommissioning IMM is close-out for the environmental compliance monitoring.
10. Publication of the EIS of the project
11. EIA Audit of the project is conducted and reviewed every three years during the project operational life cycle.
Decommissioning
1. This is carried out at the end of the project life cycle.
TIMELINES
They is no timeline on the doc
FEES
Project proponent are required to pay a registration fee of N50, 000 payableto Federal Ministry of Environment, Environmental Assessment Department in TSA (www.remita.net)
CONTACT US
Website: https://www.ead.gov.ng
EIA Contact Personnel: Director, Environmental Assessment Department
Email Address: info@ead.gov.ng.gov.ng
Phone Number: (+234) 0803 331 6437
Office: Enviromental Assessment Dept, Environment House, Independence Way, Central Area, Abuja
FG INTENSIFIES EFFORTS AT CURTAILING LASSA FEVER OUTBREAK IN NIGERIA
FG INTENSIFIES EFFORTS AT CURTAILING LASSA FEVER OUTBREAK IN NIGERIA
COMMEMORATION THE 2021 HAND WASHING DAY WITH THE THEME “OUR FUTURE IS AT HAND – LETS MOVE FORWARD TOGETHER”
Honorable Minister of Environment, Chief Sharon Ikeazor